GKNHPL or Gawar Kiratpur Nerchowk Highway Private Limited

Completed ahead of Schedule

Balance work for Four laning of Kiratpur to Nerchowk section of NH-21 (from km 12+750 to km 26+500, km 126+500 to km 158+500 including ACC link road from km 0+00 to km 2+003) Greenfield Alignment (excluding Sundernagar Bypass) (Package-2) in the State of Himachal Pradesh on Hybrid Annuity Mode Basis;

Highway No

NH-21

Project Length

47.753(km)

End of concession

June - 2038

Bonus Received

Completed ahead of Schedule

Aerial View of the Highway Modern Construction Equipment Completed Highway with Beautiful Scenery

Two/Four Laning of BRT Tiger Reserve Boundary to Bangalore Section of NH-209 (Existing chainage from km. 287.520 to km. 461.550) in the state of Karnataka on Hybrid Annuity Mode under NHDP Phase- IV

  • Type of Project: Hybrid Annuity Mode
  • State: Karnataka
  • Length of Project in KMs: 164.34 km
  • Date of Concession Agreement : December 08, 2016 (Project of Sadhbav acquired through endorsement)
  • Date of Endorsement Agreement : February 13, 2023
  • Status: Operational
  • PCOD: December 31, 2020
Aerial View of the Highway Modern Construction Equipment Completed Highway with Beautiful Scenery

Upgradation to 2 lane with paved shoulder/4 lane of Khajuwala - Poogal section (Design Chainage 0+000 to 30+812) and Poogal - Dantour - Jaggasar - Gokul - Goddu - Ranjeetpura - Charanwala - Naukh - Bap section of NH-911 (Design Chainage 1+430 to 182+725) (Total length 212.107 km) under Bharatmala Pariyojna in the state of Rajasthan on Hybrid Annuity Mode Basis

  • Completed ahead of Schedule
  • Type of Project: Hybrid Annuity Mode
  • State: Rajasthan
  • Length of Project in KMs: 212.107 km
  • Date of Concession Agreement : September 28, 2018
  • Scheduled Completion Date: March 21, 2021
  • Status: Operational
  • COD: October 30, 2021
  • Bonus: Early Completion Bonus achieved
Aerial View of the Highway Modern Construction Equipment Completed Highway with Beautiful Scenery

Balance work for Four laning of Kiratpur to Nerchowk section of NH-21 (from km 12+750 to km 26+500, km 126+500 to km 158+500 including ACC link road from km 0+00 to km 2+003) Greenfield Alignment (excluding Sundernagar Bypass) (Package-2) in the State of Himachal Pradesh on Hybrid Annuity Mode Basis

  • Completed ahead of Schedule
  • Type of Project: Hybrid Annuity Mode
  • State: Himachal Pradesh
  • Length of Project in KMs: 47.753 km
  • Date of Concession Agreement : November 26,2020
  • Scheduled Completion Date: February 08,2024
  • Status: Operational
  • COD: September 05, 2023
  • Bonus: Early Completion Bonus achieved
Aerial View of the Highway Modern Construction Equipment Completed Highway with Beautiful Scenery

4/6 Laning of Narnaul Bypass Crossing to Paniyala Mor (NH-148B) (at NH-48 Junction)=31.24 Km, Nizampur Link Road=2.76 Km & Narnaul Bypass Crossing to Pacheri Kalan=11.30 Km (NH-11) in the State of Haryana under Bharatmala Pariyojana on Hybrid Annuity Mode Basis

  • Completed ahead of Schedule
  • Type of Project: Hybrid Annuity Mode
  • State: Haryana
  • Length of Project in KMs: 45.300 km
  • Date of Concession Agreement : February 28, 2019
  • Scheduled Completion Date: March 17, 2022
  • Status: Operational
  • COD: January 09, 2021
  • Bonus: Early Completion Bonus achieved
Aerial View of the Highway Modern Construction Equipment Completed Highway with Beautiful Scenery

4-Laning of Rampur - Kathgodam section of NH-87 (New NH No.9, 109) from km 42.791 (Design Chainage km 43.446) to km 88.000 (Design Chainage km 93.226) [Package - II] in the state of Uttarakhand under NHDP Phase – III on Hybrid Annuity Mode basis

  • Type of Project: Hybrid Annuity Mode
  • State: Uttarakhand
  • Length of Project in KMs: 49.780 km
  • Date of Concession Agreement : June 02, 2016 (Project of Sadhbav acquired through endorsement)
  • Date of Endorsement Agreement: July 14, 2023
  • Status: Operational
  • PCOD: October 27, 2019
Aerial View of the Highway Modern Construction Equipment Completed Highway with Beautiful Scenery

Redesigning, Rehabilitation and Upgradation to Four Lane configuration & Strengthening of Rohna/Hassangarh to Jhajjar Section from Km 44.800 to km 80.250 (Design Chainage) (Length 35.450 km) of NH-334B in the State of Haryana on Hybrid Annuity Mode Basis

  • Completed ahead of Schedule
  • Type of Project: Hybrid Annuity Mode
  • State: Haryana
  • Length of Project in KMs: 35.45 km
  • Date of Concession Agreement : May 09, 2018 (as amended on February 13, 2019)
  • Scheduled Completion Date: December 17, 2020
  • Status: Operational
  • COD: July 31, 2020
  • Bonus: Early Completion Bonus achieved
Aerial View of the Highway Modern Construction Equipment Completed Highway with Beautiful Scenery

Redesigning, Rehabilitation and Upgradation to Four Lane configuration & Strengthening of UP/Haryana Border to Rohna Section from Km 0.00 to Km 44.80 (Design Chainage) (Length 40.500) of NH- 334B in the State of Haryana (Package-1) on Hybrid Annuity Mode Basis

  • Completed ahead of Schedule
  • Type of Project: Hybrid Annuity Mode
  • State: Haryana
  • Length of Project in KMs: 40.500 km
  • Date of Concession Agreement : May 27, 2019
  • Scheduled Completion Date: January 21, 2022
  • Status: Operational
  • COD: April 05, 2022
  • Bonus: Early Completion Bonus achieved
Aerial View of the Highway Modern Construction Equipment Completed Highway with Beautiful Scenery

Four laning of Rajauli-Bakhtiyarpur section of NH-31 (New NH-20) from Km 54+405 to Km 101+630 (Package II) on Hybrid annuity mode in the state of Bihar

  • Type of Project: Hybrid Annuity Mode.
  • State: Bihar
  • Length of Project in KMs: 47.225 km
  • Date of Concession Agreement : October 28, 2020
  • Scheduled Completion Date: April 28, 2023
  • Status: Operational
  • PCOD: April 27, 2023
Aerial View of the Highway Modern Construction Equipment Completed Highway with Beautiful Scenery

4- Laning of Dewas Ujjain section of NH-148 NG from Design Ch. 0+000 to 19+733 & Construction of 4-Lane Ujjain Bypass from Design Ch. 19+733 to 26+900 (Part-I) and construction of 4-Lane Dewas Bypass from Design Ch. 0+000 to 14+520 (Part- II) with a total design length of 41.42 km in the State of Madhya Pradesh on Hybrid Annuity Mode Basis

  • Type of Project: Hybrid Annuity Mode
  • State: Madhya Pradesh
  • Length of Project in KMs: 41.42 km
  • Date of Concession Agreement : December 11, 2020
  • Scheduled Completion Date: July 06, 2023
  • Status: Operational
  • COD: January 16, 2024